It's up to you. If you have 5 Concrete laborers who all have the same rate and you don't care to track vacations, create a Concrete Laborer resource and set the max units to 500%.

If you need to say that one of the laborers is on vacation for two weeks, then setting CL1, CL2, etc is likely better.