No. One of the setting in the Task Information dialog is to "Roll up" a task to the summary bar. That setting superimposes the bar for the selected tasks on the Summary Bar in the Gantt chart.

The rollup field (yes/no) simply indicates whether that option in the Task Information dialog is selected.

I hope this helps.
Reply With Quote
 



Other Forums: Access Forums

All times are GMT -7. The time now is 09:31 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft