#2
|
|||
|
|||
|
No. One of the setting in the Task Information dialog is to "Roll up" a task to the summary bar. That setting superimposes the bar for the selected tasks on the Summary Bar in the Gantt chart.
The rollup field (yes/no) simply indicates whether that option in the Task Information dialog is selected. I hope this helps. |
|
|