No. One of the setting in the Task Information dialog is to "Roll up" a task to the summary bar. That setting superimposes the bar for the selected tasks on the Summary Bar in the Gantt chart.

The rollup field (yes/no) simply indicates whether that option in the Task Information dialog is selected.

I hope this helps.