#1
|
|||
|
|||
![]()
No. One of the setting in the Task Information dialog is to "Roll up" a task to the summary bar. That setting superimposes the bar for the selected tasks on the Summary Bar in the Gantt chart.
The rollup field (yes/no) simply indicates whether that option in the Task Information dialog is selected. I hope this helps. |
#2
|
|||
|
|||
![]()
Thanks but I didnt understand what you mean by
[quote=JulieS;32431]That setting superimposes the bar for the selected tasks on the Summary Bar in the Gantt chart. quote] can you explain further if possible? thanks |
#3
|
|||
|
|||
![]()
The best way to understand this is to see what the option does. Create a summary tasks with two subtasks. Roll up one of the subtasks and you'll see the subtask bar appear over the summary task bar in the Gantt chart.
|
![]() |