JulieS JulieS is offline Linking predecessor twice Windows 7 64bit Linking predecessor twice Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

I'm afraid that is not possible in Project. Consider breaking the placing of the steel into two tasks -- those that can happen concurrently with Forms and then a separate tasks for those placements that require the forms to be finished.



Julie
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Linking predecessor twice arrows remain between task bars, but predecessor info disappears from task info Antares Project 1 12-14-2011 09:19 AM
MS Project 2007 Predecessor Macro dmpyne Project 1 12-14-2011 08:46 AM
Linking predecessor twice New to project - Predecessor Question geissap Project 1 01-20-2011 10:00 AM
Linking within the same document tam5070 Word 0 02-06-2009 02:21 PM
linking or something? boonders Word 2 01-07-2009 02:12 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 06:27 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft