based on your answer,
1-so by telling me to enter duration as 4 days, you are in a way telling me that, the first time I enter duration for an activity, I should first think of it as if it will be done by just one (1) full time resource? such as i should calculate "how long would it take for just one full time resource to finish this", and then i do the math myself outside, and come up with 4 days and enter that? 2-as soon as I assign 4 days, and then enter just one (1) full time resource, the project automatically multiplies 4 days by 8 hours (because lets say we had set a full day to 8 hours) to come up with 32 hours? |
#2
|
|||
|
|||
![]()
You may certainly work by either specifying duration or entering the work for each resource and letting Project calculate duration.
You expressed that you knew how long a task took one person. How long is duration. If you said you knew a painter could paint 100 sq feet of wall in 8 hours of work -- that is work. Use what ever method makes the most sense for you. You are correct -- if you set duration, Project will calculate work based upon: Duration * assignment units = Work You can specify work and Project will recalculate duration based upon: Work/Assignment units = Work. |
![]() |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
font in style definition trashed | eNGiNe | Word | 1 | 03-30-2012 05:03 AM |
How to obtain the column “C” from column “A” and “B”? | Jamal NUMAN | Excel | 2 | 02-26-2012 01:28 PM |
Can I change the horizontal scrollbar to scroll smoothly rather than column by column | carpat | Excel | 0 | 01-10-2012 09:34 AM |
Dumping styles definition | gouletp | Word | 3 | 09-06-2011 10:29 AM |
![]() |
pdfaust | Excel | 2 | 02-03-2011 03:02 PM |