No, the amount of work is the amount of effort for that particular resource. Split your screen to show the Task form in the lower pane.
Assign the resource using the Task form and enter the work in the work column. Click OK and Project will recalculate the duration required for the assigned resource to accomplish that work given the assignment units. In the case of you specifying work, project will calculate duration by: Work/Assignment Units = Duration |
|
![]() |
||||