so for instance i have 100 sf of wall to paint. when i want to calculate durations using the sf data and the productivity / worker / hour data, how can i translate this 100 sf of wall to work?
for example if i know that one worker can complete 100 sf of wall in 8 hours, then does the work become 8 hours? in other words, 1-does the work mean the amount of time required for one (1) unit to finish that entire task? 2-in general, when i have sf data, and productivity data, and when i want to translate this into ms project to come up with my duration, is the work column where I start? if not which column i start with? if work column is the place to start, then i enter resources available, assign resources and then it calculates the duration? is that the sequence? |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
font in style definition trashed | eNGiNe | Word | 1 | 03-30-2012 05:03 AM |
How to obtain the column “C” from column “A” and “B”? | Jamal NUMAN | Excel | 2 | 02-26-2012 01:28 PM |
Can I change the horizontal scrollbar to scroll smoothly rather than column by column | carpat | Excel | 0 | 01-10-2012 09:34 AM |
Dumping styles definition | gouletp | Word | 3 | 09-06-2011 10:29 AM |
![]() |
pdfaust | Excel | 2 | 02-03-2011 03:02 PM |