I only have one line entered in my resource availability list:
Available from: May 1, 2012 Available to: NA If the machine doesn't land on your site until May 1, there is no reason to enter the zero availability line -- the assumption is any date previous to May 1 the max units is zero. I am using Project Professional 2010 SP-1 |
|
![]() |
||||