I'm setting up all my resources in the resource sheet (MSP2010) and find that the "available from and to" dates seem to work in a strange way (either that or I'm trying to make them do something they're not designed to do).

My resources BECOME available for use (at 50%) on a certain date.

Lets say I can have "Brian" from the beginning of May, to work on my project. Obviously, the relevant line on the resource sheet should show "Available from May 1st at 50%".

Instead, it seems that Brian is available UNTIL ("available to") 30th April at zero percent - which is technically correct, but pretty counter-intuitive in my opinion, and tells me nothing about his availablility AFTER the beginning of May.

Is there any way to make the resource sheet show what I'm looking for?