#1
|
|||
|
|||
overtime work effecting task duration
Hi
In MS Project 2007, when you change overtime work, why task duration gets changed? - this is strange! The duration comes to less than 1 day (in decimals) when i increase the overtime work!! thanks hammad |
Tags |
overtime work |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Task duration between 2 fixed milestones | cettolox | Project | 3 | 01-24-2012 06:33 AM |
Task cannot stop once started, but cannot continue into non-work hours | sullied | Project | 3 | 12-05-2011 06:32 PM |
Work not changing duration | benoldays | Project | 0 | 02-14-2011 08:21 PM |
Work as percent of another task | JohnG10 | Project | 0 | 12-10-2010 07:51 AM |
Duration changes fail to update work effort | Panteledes | Project | 6 | 05-25-2010 02:27 PM |