Hello,
Just trying to get my head round calendars. My first task is of 4 weeks length. With the default project calendar applied ie 40 Hrs a week. So to check I know how to alter a calendar. I change the duration to 120h and the task duration changes to 3 weeks (monday to fri X3). Then I create a short week calandar (short week) of a 5 hour day/25 h week. And change the applied calendar to "short week". Save the project. And reload. I still have a 120h 3-week task. Have I overlooked something? TIA |
#2
|
|||
|
|||
![]()
Do you have resources assigned to the task? If you have resources assigned, it is the resource calendar in "charge" on a task -- unless when you assign the task calendar you select the option "Scheduling ignores resource calendars."
Julie |
#3
|
|||
|
|||
![]()
No resource appled yet.
I am however pleased to learn about the "Scheduling ignores resource calendars." option! Thanx. |
#4
|
|||
|
|||
![]()
Hi PMNewbie,
If you don't have resources assigned then either the Project Calendar (set in Project Information) or a task calendar is "ruling" the schedule. So, a couple of questions: Where/how did you change the calendar? Did you create a new calendar or modify the "Standard" calendar. I'm guessing you applied a task calendar? What version of Project are you using? You are working with Automatically scheduled tasks? Changing the calendar should not change the duration of 120 hours -- but it definitely will change the end date. I hope this helps. |
#5
|
|||
|
|||
![]()
Hi Julie,
Thanx for your continued interest!Double click on Task ie task information. Advanced -> calendar-> Assign "Short week" Ceated new calendar. 25 hrs per week Not sure if I creatred a task calendar - it is described a base calendar. project 2010 - yes auto. |
#6
|
|||
|
|||
![]()
If you press F9, does the finish date change?
|
#7
|
|||
|
|||
![]()
Hello Julie,
F9 did not help. But I created a new Calendar (again) with the required working hours. And it now works just fine. I suspect that I had done something wrong when creating the calendar teh first time. Thanks for your help. Appreciated ;-) And I will remember F9, which google tells me, forces recalculation! |
#8
|
|||
|
|||
![]()
You're welcome. It sounds like things may have been off in the other calendar. I'm glad you have it sorted and thanks for the feedback.
Julie |
![]() |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
Actual working hours per day | climbatron | Project | 2 | 12-17-2015 03:13 PM |
![]() |
PomDave | Excel | 3 | 09-05-2011 04:43 AM |
![]() |
Stan | Outlook | 2 | 08-16-2011 09:30 AM |
![]() |
mrsatchmo | Excel | 1 | 01-26-2011 08:50 AM |
emailed outlook calendar not working | Tankerman | Outlook | 0 | 12-08-2010 10:36 AM |