View Single Post
 
Old 01-13-2012, 08:22 AM
JulieS JulieS is offline Windows 7 64bit Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Hi PMNewbie,

If you don't have resources assigned then either the Project Calendar (set in Project Information) or a task calendar is "ruling" the schedule.

So, a couple of questions:
Where/how did you change the calendar?
Did you create a new calendar or modify the "Standard" calendar.
I'm guessing you applied a task calendar?
What version of Project are you using? You are working with Automatically scheduled tasks?

Changing the calendar should not change the duration of 120 hours -- but it definitely will change the end date.

I hope this helps.
Reply With Quote