Hi PMNewbie,
If you don't have resources assigned then either the Project Calendar (set in Project Information) or a task calendar is "ruling" the schedule. So, a couple of questions: Where/how did you change the calendar? Did you create a new calendar or modify the "Standard" calendar. I'm guessing you applied a task calendar? What version of Project are you using? You are working with Automatically scheduled tasks? Changing the calendar should not change the duration of 120 hours -- but it definitely will change the end date. I hope this helps. |
![]() |
|
![]() |
||||