Old 01-07-2012, 06:12 AM
pm_newbie pm_newbie is offline Windows 7 64bit Office 2010 64bit
Novice
 
Join Date: Dec 2011
Posts: 12
pm_newbie is on a distinguished road
Default calendar -reduced working hours

Hello,
Just trying to get my head round calendars.
My first task is of 4 weeks length. With the default project calendar applied ie 40 Hrs a week.

So to check I know how to alter a calendar.
I change the duration to 120h and the task duration changes to 3 weeks (monday to fri X3).
Then I create a short week calandar (short week) of a 5 hour day/25 h week.
And change the applied calendar to "short week".
Save the project.
And reload.
I still have a 120h 3-week task.
Have I overlooked something?

TIA