#1
|
|||
|
|||
![]()
I have to update a large number of devices, each during out of hours. I have a couple of weeks to do this so I want to do as many per night as possible, however I cannot do more than one at a time.
To do the upgrade there are 3 tasks that have to run sequentially on each device and it has to be completed out of hours. How can I make project not start a device upgrade if it cannot complete all three tasks during the out of hours window? |
Thread Tools | |
Display Modes | |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
sullied | Project | 3 | 12-05-2011 06:32 PM |
Split a task | fridos | Project | 2 | 05-30-2011 11:19 AM |
how to make the task starts next day if no time enough today(task can not be split) | duraid | Project | 1 | 10-25-2010 08:31 AM |
Need help with user-completed letter | Rhazdel | Word | 0 | 09-10-2010 10:59 AM |
How do i implement learnings from completed projects? | stingy | Project | 0 | 03-18-2010 02:09 AM |