View Single Post
 
Old 01-11-2012, 03:50 AM
proj proj is offline Windows XP Office 2003
Novice
 
Join Date: Jan 2012
Posts: 1
proj is on a distinguished road
Default several task must be completed out of hours, not split

I have to update a large number of devices, each during out of hours. I have a couple of weeks to do this so I want to do as many per night as possible, however I cannot do more than one at a time.
To do the upgrade there are 3 tasks that have to run sequentially on each device and it has to be completed out of hours. How can I make project not start a device upgrade if it cannot complete all three tasks during the out of hours window?
Reply With Quote