#2
|
|||
|
|||
|
Ii would create a task calendar to restrict the working hours to your "out of hours" time. Unfortunately there is not a direct method to restrict tasks from not being split over the different "out of hours" slots. The best thing I can suggest is to figure out what is the required path -- ie can one task be done one night and the other two happen another night? Then see if you can estimate how long each combination takes. If the series of 3 tasks take a total of 4 hours and your "out of hours" time ends at 11:00 pm -- then it must be started by 7:00 pm in order to finish by 11:00 pm.
|
| Thread Tools | |
| Display Modes | |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
Task cannot stop once started, but cannot continue into non-work hours
|
sullied | Project | 3 | 12-05-2011 06:32 PM |
| Split a task | fridos | Project | 2 | 05-30-2011 11:19 AM |
| how to make the task starts next day if no time enough today(task can not be split) | duraid | Project | 1 | 10-25-2010 08:31 AM |
| Need help with user-completed letter | Rhazdel | Word | 0 | 09-10-2010 10:59 AM |
| How do i implement learnings from completed projects? | stingy | Project | 0 | 03-18-2010 02:09 AM |