Hello,
Just trying to get my head round calendars. My first task is of 4 weeks length. With the default project calendar applied ie 40 Hrs a week. So to check I know how to alter a calendar. I change the duration to 120h and the task duration changes to 3 weeks (monday to fri X3). Then I create a short week calandar (short week) of a 5 hour day/25 h week. And change the applied calendar to "short week". Save the project. And reload. I still have a 120h 3-week task. Have I overlooked something? TIA |
|
![]() |
||||