Unless your summary task is manually scheduled or your calculation mode is set to "manual", the summary task start and finish are determined by the earliest start of any subtask and the latest finish of any subtask.
Take a screen shot and post the picture here (summary task expanded) and we'll try to sort it out. Julie |