  #2  
Old 01-02-2012, 02:34 PM
JulieS JulieS is offline summary task calculating from project start Windows 7 64bit summary task calculating from project start Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Unless your summary task is manually scheduled or your calculation mode is set to "manual", the summary task start and finish are determined by the earliest start of any subtask and the latest finish of any subtask.

Take a screen shot and post the picture here (summary task expanded) and we'll try to sort it out.

Julie
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
summary task calculating from project start Groups to be sorted by start date in MS Project Antares Project 3 12-09-2011 03:17 PM
summary task calculating from project start Task Start and End Dates OTPM Project 2 12-04-2011 09:14 AM
Task and Summary Durations JR_12 Project 0 10-15-2011 05:07 PM
summary task calculating from project start Custom field formula not working at summary task level abw1987 Project 3 10-05-2011 07:17 AM
summary task calculating from project start Project start date steve138 Project 4 05-20-2011 04:55 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 07:59 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft