![]() |
|
#6
|
|||
|
|||
|
By default, Project calculates variance comparing current data against Baseline data -- not Baseline1, or Baseline2. So, the ability to copy a baseline into one of the "spare" baselines and then re-baseline is designed to take advantage of the built-in calculation.
The reasons why a project manager re-baselines are many. In most circumstances it is negotiated with the sponsoring organization as it is used for comparison. If you re-baseline after tracking any variance created by tracking is removed when the new baseline is saved as it sets Baseline data = actual data on the tracked tasks. I hope this helps. Julie |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Calculating Weekend Allowance | WinIDS | Excel | 6 | 09-02-2011 01:27 AM |
Calculating dates
|
Daria11 | Word VBA | 1 | 06-08-2011 06:54 PM |
| calculating points and division in excel | edward masoya | Excel | 1 | 05-09-2011 06:31 AM |
Calculating age at date
|
jamierbooth | Excel | 2 | 02-22-2011 03:35 AM |
| Calculating Form Fields in Microsoft Word | wubba80 | Word | 1 | 06-25-2010 12:42 AM |