JulieS JulieS is offline calculating duration Windows 7 64bit calculating duration Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

By default, Project calculates variance comparing current data against Baseline data -- not Baseline1, or Baseline2. So, the ability to copy a baseline into one of the "spare" baselines and then re-baseline is designed to take advantage of the built-in calculation.

The reasons why a project manager re-baselines are many. In most circumstances it is negotiated with the sponsoring organization as it is used for comparison.

If you re-baseline after tracking any variance created by tracking is removed when the new baseline is saved as it sets Baseline data = actual data on the tracked tasks.

I hope this helps.
Julie
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Calculating Weekend Allowance WinIDS Excel 6 09-02-2011 01:27 AM
calculating duration Calculating dates Daria11 Word VBA 1 06-08-2011 06:54 PM
calculating points and division in excel edward masoya Excel 1 05-09-2011 06:31 AM
calculating duration Calculating age at date jamierbooth Excel 2 02-22-2011 03:35 AM
Calculating Form Fields in Microsoft Word wubba80 Word 1 06-25-2010 12:42 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 09:10 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft