Scaffold Scaffold is offline Using WORKDAY with fractional day lengths Windows XP Using WORKDAY with fractional day lengths Office 2003
Advanced Beginner
Using WORKDAY with fractional day lengths
 
Join Date: Oct 2009
Location: Moscow, Russia
Posts: 36
Scaffold is on a distinguished road
Default

Hi Tony!



I see no problem with my solution. It works exactly as intended, adding fractions of days and excluding weekends. Duration of workday is accounted for by calculating of the fraction of the day it takes to complete the task. Am I overlooking something?

Thanks for the link, but in my company we have to stick to the officially approved software. Thanks for the help, anyway.
Reply With Quote
Reply



Other Forums: Access Forums

All times are GMT -7. The time now is 07:31 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft