Hi Tony!

I see no problem with my solution. It works exactly as intended, adding fractions of days and excluding weekends. Duration of workday is accounted for by calculating of the fraction of the day it takes to complete the task. Am I overlooking something?

Thanks for the link, but in my company we have to stick to the officially approved software. Thanks for the help, anyway.