Hi Colin!

There's 8 working hours in each day. That's why I converted days from hours as 1/8.

For the starters, we can accept your assumption and see what happens then. But if you assume that each working day lasts 24 hours, then 2 hours of my work should be converted to 1/4 of that day, right?

Thanks in advance!
Reply With Quote
 



Other Forums: Access Forums

All times are GMT -7. The time now is 08:09 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft