Imagios Imagios is offline Reporting ManDays on people not fully assigned to the Project Windows 7 64bit Reporting ManDays on people not fully assigned to the Project Office 2010 64bit
Novice
Reporting ManDays on people not fully assigned to the Project
 
Join Date: Oct 2011
Posts: 18
Imagios is on a distinguished road
Default

Hello,
may be I do something wrong, but if I go there I see the hours/days they accualy have to work not the days their are assigned to...
for example if someone is assigned for two hours I need a report showing is was working two hours as well as a report that he was assigned for one day. Its for internal cost reporting...
Reply With Quote
  #2  
Old 10-06-2011, 04:23 AM
OTPM OTPM is offline Reporting ManDays on people not fully assigned to the Project Windows 7 32bit Reporting ManDays on people not fully assigned to the Project Office 2010 32bit
Expert
 
Join Date: Apr 2011
Location: West Midlands
Posts: 981
OTPM is on a distinguished road
Default

Hi
It sounds like you are not using MS Project correctly. You can record Scheduled Activity and Actual Activity against each resource together with dates and times.
What are you actually looking for?
Tony
Reply With Quote
  #3  
Old 10-06-2011, 04:37 AM
Imagios Imagios is offline Reporting ManDays on people not fully assigned to the Project Windows 7 64bit Reporting ManDays on people not fully assigned to the Project Office 2010 64bit
Novice
Reporting ManDays on people not fully assigned to the Project
 
Join Date: Oct 2011
Posts: 18
Imagios is on a distinguished road
Default

OK may be I express my self wrong...

One thing is and that is what I need to see how much time one accualy spends on the project, that I can find in the team view...

Second thing is for internal reasons all the people contributing to the project are reported as fully assigned. That means if his task start at the 1.11. and ends on 15.11. even he is assined only for 5% and works on the task few hours, I need a report showing that he worked two weeks, in this case 10 Mandays.
Reply With Quote
  #4  
Old 10-06-2011, 10:00 AM
OTPM OTPM is offline Reporting ManDays on people not fully assigned to the Project Windows 7 32bit Reporting ManDays on people not fully assigned to the Project Office 2010 32bit
Expert
 
Join Date: Apr 2011
Location: West Midlands
Posts: 981
OTPM is on a distinguished road
Default

Hi
In that case, irrespective of how long they ACTUALLY spend doing the tasks you can assign then as 100% on the task for the given period. The you can use the resource usage report to show how long each person is assigned to the project.
OR
You can create a custom view in Project with the information you need to show. Then export the data to Excel and change the start and Finish columns just to show the dates and not the times if you still want Project to just show the ACTUAL hours spent on the project.
Hope this helps.
Tony
Reply With Quote
  #5  
Old 10-07-2011, 04:29 AM
Imagios Imagios is offline Reporting ManDays on people not fully assigned to the Project Windows 7 64bit Reporting ManDays on people not fully assigned to the Project Office 2010 64bit
Novice
Reporting ManDays on people not fully assigned to the Project
 
Join Date: Oct 2011
Posts: 18
Imagios is on a distinguished road
Default

I tried the first solution, but since the people have more tasks in the same period assigned them, to put them as 100% per task has a result of people shown as overloaded in the resources diagram, I thought there is a simpler solution in Project for that...
Im sure Im not the only one having the issue that people assigned to projects do accutualy as well other things than to work only on the project... but this is more a topic of accurate planning and as well about a conflict of theory and praxis
Reply With Quote
  #6  
Old 10-07-2011, 04:47 AM
OTPM OTPM is offline Reporting ManDays on people not fully assigned to the Project Windows 7 32bit Reporting ManDays on people not fully assigned to the Project Office 2010 32bit
Expert
 
Join Date: Apr 2011
Location: West Midlands
Posts: 981
OTPM is on a distinguished road
Default

Hi
Project will only report on planned and actual assignment durations. It cannot report anything in between.
As I suggested earlier you can export assignment information to Excel and then in nthe Start and Finish columns in Excel you can change the date format so that it reports on the day only and not the time.
Hope this helps.
Good luck.
Tony (OTPM)
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Reporting ManDays on people not fully assigned to the Project Converting Powerpoint into Fully Accessable PDFs KCD123 PowerPoint 4 09-28-2011 10:03 AM
Hyperlink assigned sounds do not play Starscream PowerPoint 0 03-08-2011 02:14 PM
Resource Overallocation Reporting Mutso Project 0 11-05-2010 12:27 PM
Reporting ManDays on people not fully assigned to the Project Outlook 2007 Not Fully Closing LabanM Outlook 1 09-28-2010 02:27 PM
Project Reporting vickib1 Project 0 09-08-2010 03:11 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:13 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft