#1
|
|||
|
|||
First To Finish Task Scheduling
In MS Project 2010, how to I schedule a task to finish when the first of a series of tasks finishes?
e.g. Task A Task B Task C Task D I want to schedule Task D to start after whichever of Task A, B, or C finishes first. |
|