Default First To Finish Task Scheduling

In MS Project 2010, how to I schedule a task to finish when the first of a series of tasks finishes?

e.g.

Task A
Task B
Task C

Task D
I want to schedule Task D to start after whichever of Task A, B, or C finishes first.