rinalgi1 rinalgi1 is offline MS Project 2010 Synch to task list Windows XP MS Project 2010 Synch to task list Office 2010 64bit
Novice
MS Project 2010 Synch to task list
 
Join Date: Sep 2011
Posts: 1
rinalgi1 is on a distinguished road
Default MS Project 2010 Synch to task list


Hi Everybody,
my issue : when I update the %Complete with 100% of task entry through SharePoint after the Synchronisation the same task in MS Project 2010 becomes 99%... Someone has an idea why 100% becomes 99% ?
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
MS Project 2010 Synch to task list Insert task from another project? StefanSt Project 3 08-28-2011 12:21 PM
Linked Outlook Task List Requires Login jlucas759 Outlook 0 02-02-2011 07:15 AM
Printing out task list smartbinhire Outlook 0 08-10-2010 03:53 AM
Outlook issue--task list Renee Arena Office 0 01-23-2006 11:09 AM
Linking a SharePoint meeting to a Project task. mnollar Project 0 12-13-2005 03:58 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 09:00 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft