![]() |
#1
|
|||
|
|||
![]() Hi Everybody, my issue : when I update the %Complete with 100% of task entry through SharePoint after the Synchronisation the same task in MS Project 2010 becomes 99%... Someone has an idea why 100% becomes 99% ? |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
StefanSt | Project | 3 | 08-28-2011 12:21 PM |
Linked Outlook Task List Requires Login | jlucas759 | Outlook | 0 | 02-02-2011 07:15 AM |
Printing out task list | smartbinhire | Outlook | 0 | 08-10-2010 03:53 AM |
Outlook issue--task list | Renee Arena | Office | 0 | 01-23-2006 11:09 AM |
Linking a SharePoint meeting to a Project task. | mnollar | Project | 0 | 12-13-2005 03:58 PM |