#1
|
|||
|
|||
![]()
I've plotted 4 milestones on the same line by using the rollup options to roll the subtasks to the summary and then collapsing the sub-tasks view. But by doing so, the predecessor dependency links disappear if I have to print chart. Is it possible to have the dependency links to point to their respective milestones on the summary bar itself?
Thanks |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
Exporting Gantt Chart to MS Word 2007 | earweed | Project | 4 | 06-02-2011 09:21 AM |
Updating Excel Chart Links | fermat | PowerPoint | 0 | 07-09-2010 04:29 PM |
Custom animating a line chart by series and category. | Gahzi | PowerPoint | 0 | 05-19-2009 11:53 AM |
![]() |
Nance | Project | 2 | 12-09-2008 01:59 PM |
![]() |
Steve Sells | Project | 2 | 11-09-2005 08:12 PM |