Hi
You can have dependency links on a Summary task, however it is not good practice to do so as it would be unclear which of the child tasks the dependency actually applies to.
If you are using Project 2010 you can actually copy selective tasks to a Timeline chart which may give you what you want.
Hope this helps.
Tony(OTPM)