#1
|
|||
|
|||
![]()
I have several calendars, one for 365 days a year without holidays, for tests like microbiology incubation, another for 7 days a week but allow holidays used during crunch time, and 5 days a week, a normal one.
I believe this causes problem with my critical path calculation, here's what happened - Task 1 uses 365 days calendar, takes 5 days from Mon-Fri, Task 2 follows and uses 5 d/w calendar, takes 2 days from next Mon-Tue. The critical path calculation shows task 1 has 2 slack days, not in critical path ![]() I tried to use Options>Calculation and set "Tasks are critical if slack is less than or equal to" as 2 days, but it shows too many tasks ![]() Anyone has any suggestion on how to show the true critical paths ![]() |
Tags |
cpa; weekend |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
b0x4it | Word VBA | 4 | 05-18-2011 11:50 PM |
HELP! Rebuilt box & IRM lock out of critical docs | markcal | Office | 0 | 04-25-2010 11:45 AM |
Template path question | phreeq | Word | 3 | 02-22-2010 05:08 PM |
![]() |
bjtrain83 | Word | 1 | 01-10-2010 02:36 PM |
![]() |
Ziggy1 | Word VBA | 1 | 09-29-2006 07:55 PM |