Thread: [Solved] Critical Path w/ 2 Calendars
View Single Post
 
Old 07-26-2011, 04:35 PM
AndreT AndreT is offline Windows XP Office 2000
Novice
 
Join Date: Jan 2011
Location: So. Ca
Posts: 7
AndreT is on a distinguished road
Default

Hi, Kimberly -

My problem is the schedule shows Task 2 as the only task in the critical path.

I want to know if there is any alternative in MS Project to show Task 1 in critical path even though it has 2 days slack time, Task 2 can not move any further ahead.

If no other alternative, I'll have to add a 2 day dummy task and watch it, or go back to option 2 days.