Hi, Kimberly -
My problem is the schedule shows Task 2 as the only task in the critical path.
I want to know if there is any alternative in MS Project to show Task 1 in critical path even though it has 2 days slack time, Task 2 can not move any further ahead.
If no other alternative, I'll have to add a 2 day dummy task and watch it, or go back to option 2 days.