#1
|
|||
|
|||
Having problems with Duration calculations.
I have Type set to Fixed Work, as I want Duration to adjust based on the Resources I add to the ask, leaving the Work static. I have one resource setup to work 8hrs/day, and a second resource to work 4hrs/day. I set the Work to 5d for a task. However, when I assign Resource 1 and Resource 2 to the task, each @ 75%, the Duration is set for 3.33d. I would assume it should be set for 4.44d based on 40hrs (5d) / 9hrs (6hr + 3hr). Where am I going wrong with my calculations?
|
#2
|
|||
|
|||
More details: best I can tell, it's taking the complete time period (ex: 80hrs), and splitting it evenly over the two resources (ex: 40hrs each), and then the duration is based on whoever takes the longest to complete their 40hrs. That's not what I want. I want the duration to calculate based on their combined hrs/day (ex: they combine for 9hrs/day, how long to complete 80hrs). Any suggestions would be greatly appreciated. This is driving me crazy.
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Outlook Problems | komptek | Outlook | 0 | 10-30-2007 03:28 PM |
Signature problems | kim11vagabond | Outlook | 1 | 01-17-2007 02:53 PM |
Word Editor Problems | steve@pubagain | Outlook | 2 | 10-19-2006 11:32 PM |
Problems w/BCM updates? | Godwulfe | Outlook | 0 | 08-04-2006 09:22 AM |
Problems with Bcc | beadsworldwide | Outlook | 3 | 02-01-2006 03:34 PM |