Hi,
Good Morning. But still I could not open the file. (Please refer to the attached file for the error message. Regards, B.Srinivasa Rao |
#2
|
|||
|
|||
![]()
Hi
The project file was saved in 2003 format. Have you tried download the converter from the Microsoft website? If not try downloading the converter and let me know how you get on. Tony (OTPM) |
#3
|
|||
|
|||
![]()
Hi,
Yes I did the installation (i.e. SP3). Alternatively, Can I ask you to show the steps / screen shots for creating custom field by myself. (Which version you are using for editing) Thanks & regards, B.Srinivasa Rao |
#4
|
|||
|
|||
![]()
Hi
Open your plan and apply Resource Sheet View showing. Place your cursor over the heading of the Type column then right click and select insert column. Select the Text1 field from the drop down list. You will also have the option to rename the field, in the sample I sent you I renamed it to Resource2. Type in Resource2 and press enter. You will now have a standard column called Resource and next to it a column called Resource2. I then copied all the Auditee names to the new column. Hope this is what you want. I cannot provide screen shots as I am using Project 2007 and 2010. Good luck. Tony(OTPM) |
#5
|
|||
|
|||
![]()
Hi,
a) I added 'Resource2' in 'Resource Sheet' But how do I select the 'Resource2' in 'GanttChart' view. (I need Resources in TWO different columns in 'GanttChart' view) b) Please send me the 2007 screenshots. I have the 2007 version in my home pc) Thanks & regards, B.Srinivasa Rao |
#6
|
|||
|
|||
![]()
Hi
Simply apply your Gantt Chart View and then right click over any column header and insert the Text1(Resource2) field column into your Gantt Chart view. Tony (OTPM) |
#7
|
|||
|
|||
![]()
Hi,
I added 'resource2' to Gantt Chart View. But I couldnot get the dropdown menu for 'Resource2 view'. Please refer attachments. Thanks & regards, B.Srinivasa Rao |
![]() |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
MS Project Resource Chart | fherbert | PowerPoint | 0 | 09-09-2010 12:20 PM |
Project Server 2003 | Semperfi5000 | Project | 0 | 03-03-2010 02:58 PM |
Project Server 2003 SP2 | Project | 15 | 01-25-2007 03:52 AM | |
![]() |
dave | Project | 3 | 05-22-2006 06:29 PM |
![]() |
SteveGold | Office | 3 | 11-28-2005 06:35 PM |