OTPM OTPM is offline Locking resource for over-allocation resolution Windows 7 32bit Locking resource for over-allocation resolution Office 2010 32bit
Expert
 
Join Date: Apr 2011
Location: West Midlands
Posts: 981
OTPM is on a distinguished road
Default

Hi Lawrence
I am not sure that reducing the Assignment Units against each resource is the right way to do it as if a task is scheduled to a given amount of time then more resource should be added in order to achieve it in less time. However if you really want to do it the way you suggest then follow these steps:
1. Select Task Usage View.
2. Insert two new columns to the view:
- Overallocated
- Assignment Units
3. Filter the Overallocated column to "Yes".
4. Then change the assignment units for each resource until the Overallocated column reads "No".
Hope this helps.
Good luck.
Tony
Reply With Quote
 

Tags
gantt, over-allocation, resources

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Resolution mismatch Adforum PowerPoint 5 05-25-2011 12:24 PM
Locking a Form lafranceds Word 1 12-12-2010 11:40 AM
Locking resource for over-allocation resolution Graphics resolution Roscoe Drawing and Graphics 5 07-02-2010 07:43 AM
locking out word joe Word 0 11-19-2009 02:09 AM
Locking Text Boise User Word 0 01-24-2009 01:55 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:37 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft