Hi
First of all dates are assigned to a task not a resource. This is why it will not work.
You can do what you want using the task view and put a formula in a custom field.
You could also consider using the "Status" column which will indicate whether or not a task is running late.
Hope this helps.
Tony
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Send e-mail message in Finish & Merge CDTom Mail Merge 1 08-24-2012 12:52 AM
Automatic resouce assignment of remaining unallocated units philk Project 0 05-04-2011 04:57 PM
Resource Usage sheet - options Andy Bain Project 1 11-05-2010 12:42 PM
Accessing Assignment Detail Data in Task Usage View CGM3 Project 0 10-05-2010 05:56 AM
Finish Variance in Resouce Usage View Help with Interim Baseline Variance poyns Project 1 05-27-2010 10:59 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 08:06 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft