In Microsoft Project, a View is defined as a Table plus a Filter plus a Group plus a Screen. the Table is the set of columns you want to see. The Filter displays only the rows you want to see. The Group organizes rows into Groups with similar attributes or characteristics. The Screen is the graphical based image displays on the right side of the View, such as a Gantt Chart screen or a Task Usage screen.
To create the views you have described, you would need to create a custom Table for each View, and you might need to create a custom Filter for some of the Views. To learn how to create a custom View, you might want to watch one of my recent YouTube videos on this subject: https://youtu.be/uf1cZC-fKnw Hope this helps. |
|
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Project not updating task when project start date changed | Nextenso | Project | 3 | 07-08-2023 11:55 AM |
| Reports created in Project 2016 not viewable in Project 2010 | Murali Narayanan | Project | 0 | 05-23-2019 03:59 PM |
| How to modify the Gantt chart bar styles (label of values) in project center (WPA) (MS Project 2010) | Cedahlia | Project | 0 | 04-21-2018 10:29 PM |
| Project task numbering changed after linking item in subproject to m aster project | rrs_2017 | Project | 0 | 09-06-2017 06:07 AM |
| Microsoft Project Server, Microsoft Project Online and Project Web App - Whats the difference? | chocolateCupcakes | Project | 1 | 02-11-2017 12:25 PM |