#1
|
|||
|
|||
Ressources on Parallel Tasks
Hello Guys, i have a Project, where I have two Tasks. One lasts one year and has a work duration of one full time equivalent(FTE), the other one 2 years but only need half FTE. Therefore one FTE would be enough to finish both tasks after two years. I want to enter into project for the first task 1 FTE over the full duration, and 50% FTE over two years. how can I make Project to automatically plan the FTE for 100% on the second task? Thank you |
#2
|
|||
|
|||
Assuming that the same resource is working on both of these tasks, I would set the Duration of each task to 1 year, set a Finish to Start Dependency between them, and then assign the resource at a Units value of 100%. This way, both tasks will be finished over the 2-year time span without having to deal with overallocations. Just a thought. Hope this helps.
|
#3
|
|||
|
|||
Thanks, is there also a solution to not adjust the duration?
|
#4
|
|||
|
|||
The situation you describe with your intended solution will create a resource overallocation for the first year. So, no, the solution I propose would work the best without creating an overallocation.
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Tasks - Ressources report ? | cioknarf | Project | 0 | 12-14-2021 03:17 AM |
Check amount of free ressources | Albert HAFENSCHER | Project | 0 | 06-28-2017 12:51 AM |
Parallel animation schemes | Chuker | PowerPoint | 2 | 03-04-2016 12:44 PM |
How to create "parallel" tasks? | A.S. | Project | 4 | 10-29-2015 03:06 PM |
Auto-level resources for parallel tasks with fixed work | cineasta | Project | 5 | 11-21-2013 01:03 PM |