I have a master project with 4 sub-projects. Each sub-project is on a different baseline number (I.e. baseline2, badeline7, etc…).
Is there a way to show the start date of the most recent baseline of each sub-project in one column on the master project? As in have a baseline start date column in the master project, but it pulls the dates from the last-saved baseline of each sub-Project instead of having to have a column for baseline1 start, baseline3 start, baseline7 start, etc… |
|
![]() |
||||