#1
|
||||
|
||||
|
I've replicated your question in MSP 2010 and the finish date changes with duplicate resources.
Maybe check that you've got "auto-scheduled" task mode for the task and not "manually scheduled". =jerome Planners' Place |
|
#2
|
|||
|
|||
|
Hi Jerome, I hope you are fine.
Thank you very much for taking the time to write me your reply to my question. I verified and the task is in auto schedule mode, so I believe it is a Project 2010 bug related to Task type since fixed work task type is not behaving as expected. Once again, thank you so much for your time and effort to help. Best regards, Alberto Villanueva. |
|
| Tags |
| fixed work, resource allocation, task duration |
| Thread Tools | |
| Display Modes | |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Is it a bug or not ? Ms Project randomly changes project's tasks resources name when re-open file ? | capsule | Project | 1 | 11-26-2017 06:45 AM |
| MS Project 2013 - Manually set up the finish date ??? | nicolafusconi | Project | 1 | 03-28-2017 08:40 AM |
| flag to indicate finish date does not equal baseline finish date | TCB | Project | 3 | 08-06-2014 02:49 PM |
Units not properly updated after a Finish Date Change
|
zi1 | Project | 1 | 08-04-2012 05:55 AM |
| MS Project able to import actual start and or actual finish date from Excel? | mhacker | Project | 0 | 04-26-2010 11:29 AM |