![]() |
|
![]() |
|
Thread Tools | Display Modes |
|
#1
|
||||
|
||||
![]()
assuming this task is linked to other tasks with a FS relationship, change the successor logic to SS.
E.g. if the task you want to extend its finish date is ID3 and its successor is ID4, in the successor column of ID3, enter, 4SS. =jerome plannersplace.com |
#2
|
|||
|
|||
![]()
It is currently linked with a SS and is linked to a milestone. I am basically trying to push the end date of the task without affecting the other dates in the milestone.
|
![]() |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
Project 2013 - Change GANTT Bar Colour By Main Task Date | CaelanT | Project | 1 | 02-09-2015 12:50 PM |
![]() |
RJTMEYER | Project | 3 | 08-22-2014 07:38 AM |
Rollup Summary Tasks to Project Summary Task | shep555 | Project | 1 | 05-24-2014 12:28 PM |
How to get project to automatically pull in task dates? | Moe Szylak | Project | 2 | 04-26-2012 12:37 PM |
![]() |
sjodom | Project | 3 | 12-04-2011 08:45 AM |