ProjectPlanner ProjectPlanner is offline Adjusting the end date on a Task in MS Project without affecting the dates on other tasks? Windows 10 Adjusting the end date on a Task in MS Project without affecting the dates on other tasks? Office 2019
Advanced Beginner
 
Join Date: Mar 2021
Location: UK
Posts: 75
ProjectPlanner is on a distinguished road
Default

assuming this task is linked to other tasks with a FS relationship, change the successor logic to SS.

E.g. if the task you want to extend its finish date is ID3 and its successor is ID4, in the successor column of ID3, enter, 4SS.

=jerome


plannersplace.com
Reply With Quote
  #2  
Old 04-14-2021, 08:39 AM
Miami3005 Miami3005 is offline Adjusting the end date on a Task in MS Project without affecting the dates on other tasks? Windows 10 Adjusting the end date on a Task in MS Project without affecting the dates on other tasks? Office 2016
Novice
Adjusting the end date on a Task in MS Project without affecting the dates on other tasks?
 
Join Date: Apr 2021
Posts: 2
Miami3005 is on a distinguished road
Default

It is currently linked with a SS and is linked to a milestone. I am basically trying to push the end date of the task without affecting the other dates in the milestone.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Project 2013 - Change GANTT Bar Colour By Main Task Date CaelanT Project 1 02-09-2015 12:50 PM
Adjusting the end date on a Task in MS Project without affecting the dates on other tasks? MS Project to detect task level changes and record a date modified in custom field RJTMEYER Project 3 08-22-2014 07:38 AM
Rollup Summary Tasks to Project Summary Task shep555 Project 1 05-24-2014 12:28 PM
How to get project to automatically pull in task dates? Moe Szylak Project 2 04-26-2012 12:37 PM
Adjusting the end date on a Task in MS Project without affecting the dates on other tasks? MS Project Start Dates not matching the Status Date sjodom Project 3 12-04-2011 08:45 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:49 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft