#1
|
|||
|
|||
|
I am doing a programme which has many identical tasks in different locations, in this case it is building a road. So the asphalting for example is a task with many indented sub tasks below it. Each sub task uses the same resources. Is there a way to enter these once and copy and paste to the tasks? When I tried this the resources copied but all at 100% usage, whereas labourers should be 700%, trucks 200% etc.
|
|
|
|