![]() |
#1
|
|||
|
|||
![]()
I am doing a programme which has many identical tasks in different locations, in this case it is building a road. So the asphalting for example is a task with many indented sub tasks below it. Each sub task uses the same resources. Is there a way to enter these once and copy and paste to the tasks? When I tried this the resources copied but all at 100% usage, whereas labourers should be 700%, trucks 200% etc.
|
![]() |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
Is it a bug or not ? Ms Project randomly changes project's tasks resources name when re-open file ? | capsule | Project | 1 | 11-26-2017 06:45 AM |
HOTFIX JUNE 2013, ISSUE with copying and pasting tasks with pre-existing links | cathalm8 | Project | 1 | 04-14-2015 01:34 PM |
![]() |
cineasta | Project | 5 | 11-21-2013 01:03 PM |
![]() |
rickw262 | Project | 1 | 01-18-2013 04:46 AM |
Changing resources against tasks with actual values | joday48 | Project | 3 | 06-28-2012 05:13 AM |