#1
|
|||
|
|||
Project reverts to 8 hours for first working day with a 9 hour calendar
I have started a new programme and changed the calendar to a 9 hour working day. However, Project shows the first working day as 8 hours with the remainder as 9. If I change the hours on the resource usage sheet from 8 to 9 the Gantt chart then shows a duration of 0.89 days Can anyone help with this? |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Project Calendar not working | Adamadament | Project | 0 | 09-11-2018 12:47 AM |
Microsoft Project Extened Working Hours with overtime | faomari | Project | 0 | 08-15-2017 06:10 AM |
Project Calendar - working days have varying hours | BarryB | Project | 1 | 11-30-2016 07:36 AM |
24 hour task calendar doesn't show a day?? | benl | Project | 3 | 12-31-2015 02:55 PM |
calendar -reduced working hours | pm_newbie | Project | 7 | 01-17-2012 10:34 AM |