![]() |
|
|
|
#1
|
|||
|
|||
|
Hi,
I'm about to work with a new client whose working time each day varies - its fair to say their working hours are non-standard as below. Monday is 8am to 5pm Tues to Thurs is 7am to 5pm Friday is 7am to 3pm Before I start to work them I've been thinking about how I could accurate capture duration data on projects plans that we will be developing going forward. Its a given that I need to align the settings in the 'Calendar options for this project' with the project calendar, otherwise durations and work estimates could be wrong or inaccurate. So, given this non-standard shift pattern, how best should I reflect the working hours in the calendar options to ensure symmetry between the two. Thanks in advance for your help. |
|
#2
|
|||
|
|||
|
You are correct that you only get to define a "day" and a "week" once. i would still likely work with a day = 8hrs and a week = 40hrs as the hours do add to 40. As long as you have set the working calendar (Change working time) correctly, it should still schedule fine. If you enter a two day duration task that starts Tuesday morning at 7:00 am, it will finish 16 working hours later.
|
|
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
Calculate Average Time Elapsed in Days, hours and minutes
|
Nina46 | Excel | 9 | 09-11-2015 02:09 AM |
| My emails don't come into Outlook 2013 for hours or even days after they are accessable via Yahoo | Annie1 | Outlook | 0 | 08-20-2014 10:16 AM |
| showing calendar days by keeping normal workday calendar | ketanco | Project | 11 | 11-01-2013 08:27 AM |
Calculate difference by days and hours
|
alysolyman | Excel | 6 | 05-13-2013 02:19 AM |
calendar -reduced working hours
|
pm_newbie | Project | 7 | 01-17-2012 10:34 AM |