#1
|
|||
|
|||
|
Hi everybody,
I'd like to thank you in advance for answering to my first post I have the following problem with MS Project 2019: I have a project plan where I have two resources with 20% capacity units( 8 hours per week). I want to assign them a task that last 8 hours ( 4 hours per person). Now MS Project is distributing there time linear, meaning 1,6 hour per days which gives me a duration of 2,5 days. So far so normal, but I want to know if there is the possibility to tell MS Project that the resource is working 4 hours on this one day and automatically subtracts the amount from the weekly total? It gives me a warning that my resource is overworked even though from a weekly total perspective it is not. Only half the weekly hours were used. On one day, but still. The reason behind this, that even though the person can only spend 8 hour a week, I can assign him to a video call workshop that lasts say 8 hours but the rest of the week the resource can concentrate on other projects. Is there a way to do this, without creating a manual calendar for each person. Normally the hours should be evenly distributed by days, this is just for special circumstances. I tried to find help with the forum search, but don't know what to search for. BR |
|
| Tags |
| capacity, daily, weekly |
| Thread Tools | |
| Display Modes | |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Creating 2 percentage fields to show the progress from week to week | Loay harhash | Project | 0 | 04-03-2018 03:26 AM |
| Project 2013 - resource capacity column | and | Project | 3 | 02-11-2015 07:10 AM |
MS Project Resource Capacity and Auto-levelling
|
Senor_Babs | Project | 2 | 11-01-2014 02:46 PM |
Week by week report
|
thedeadzeds | Excel | 3 | 11-16-2013 02:06 AM |
5 days/week during planning & 7 days/week during implementation
|
sanlen | Project | 1 | 06-25-2012 04:17 PM |