Identify Active Predecessor
Hi,
I am new to ms project and I am creating a timeline, I was hoping there was a way to easily identify what predecessor is driving the schedule when there are multiple predecessors on one task. eg. 36SS,24FS+4 wks,35SS It would bold, or underline or someway show that the one task is driving the schedule and the others are not. Thanks in advance!! |
|