![]() |
|
#1
|
|||
|
|||
|
Hi
I am importing activities from an Excel spreadsheet into MSProject and the Finish date is two days less than in Excel! I.e. if the Finish date in Excel is 10/6/2019, then it is 8/6/2019 in Project! I am also importing the duration. If I adjust the Finish date, the duration also changes, which is logical. But I can't figure out why Start + Duration is not equal to Finish. Thanks for any advice! |
|
#2
|
|||
|
|||
|
Fixed - Finish date imports OK if I do not also import Duration.
|
|
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
% completion changes finish date?
|
Puddlerunna | Project | 9 | 11-25-2014 06:16 AM |
| what to put in to schedule for dealing with overall finish date | ketanco | Project | 7 | 10-30-2014 02:25 PM |
| flag to indicate finish date does not equal baseline finish date | TCB | Project | 3 | 08-06-2014 02:49 PM |
Baseline1 estimated finish - export to excel - data disconnect. - MSProject 2010 SP1
|
stct | Project | 1 | 04-23-2013 05:11 AM |
how to calculate backwards from a set finish date
|
ketanco | Project | 1 | 02-07-2013 06:50 AM |