Microsoft Office Forums

Go Back   Microsoft Office Forums > >

Reply
 
Thread Tools Display Modes
  #1  
Old 07-11-2019, 07:33 AM
cdfj cdfj is offline MSProject imports Finish date incorrectly Windows 7 32bit MSProject imports Finish date incorrectly Office 2007
Novice
MSProject imports Finish date incorrectly
 
Join Date: Nov 2012
Posts: 6
cdfj is on a distinguished road
Default MSProject imports Finish date incorrectly

Hi
I am importing activities from an Excel spreadsheet into MSProject and the Finish date is two days less than in Excel! I.e. if the Finish date in Excel is 10/6/2019, then it is 8/6/2019 in Project! I am also importing the duration.





If I adjust the Finish date, the duration also changes, which is logical. But I can't figure out why Start + Duration is not equal to Finish.



Thanks for any advice!
Reply With Quote
  #2  
Old 07-12-2019, 04:04 AM
cdfj cdfj is offline MSProject imports Finish date incorrectly Windows 7 32bit MSProject imports Finish date incorrectly Office 2007
Novice
MSProject imports Finish date incorrectly
 
Join Date: Nov 2012
Posts: 6
cdfj is on a distinguished road
Default

Fixed - Finish date imports OK if I do not also import Duration.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
MSProject imports Finish date incorrectly % completion changes finish date? Puddlerunna Project 9 11-25-2014 06:16 AM
what to put in to schedule for dealing with overall finish date ketanco Project 7 10-30-2014 02:25 PM
flag to indicate finish date does not equal baseline finish date TCB Project 3 08-06-2014 02:49 PM
MSProject imports Finish date incorrectly Baseline1 estimated finish - export to excel - data disconnect. - MSProject 2010 SP1 stct Project 1 04-23-2013 05:11 AM
MSProject imports Finish date incorrectly how to calculate backwards from a set finish date ketanco Project 1 02-07-2013 06:50 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 10:34 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft